Phoenix ME has re-engaged on the 20 Ropemaker project an 27 storey commercial tower what integrates into urban realm and is targeting BREEAM Outstanding. It is designed to prioritize tenant wellbeing with five roof terraces and balconies to most floors.
High and low-level first fix works are progressing well, with installations currently underway across 18 of the 20 available floors, including the roof plant area. Ceiling void closures have commenced, moving the works into the second fix phase. Additionally, critical infrastructure installation is complete, and commissioning activities are now in progress.
Barcol-Air UK has supplied the VAV terminals for this project. With commissioning now well underway, 20 Ropemaker continues to move steadily towards completion.